Hyperscale Data says Michigan AI project needs $74.8 million more

Hyperscale Data said in a regulatory filing that its Michigan AI data center project will require a further $74.8 million from November 2026 through March 2027, and warned that substantial doubt exists about its ability to continue as a going concern.

The company said its available funds and financing are insufficient to cover planned spending and obligations over the next 12 months. At the end of September, it had $17 million in unrestricted cash and $231 million in current liabilities; it had sold about 1,113 BTC since the end of July for about $74 million. The project’s estimated construction and equipment costs are $122.1 million, of which $47.3 million had been paid by October; an agreement with an AI customer could be worth up to $1.2 billion, contingent on two customer renewals and the company’s performance.